The photos below show a record of progress of the replacement of Teston Lock Landing Stages:
Upstream before works commence

Downstream before works commence

9th Oct - Old downstream landing stage removed

20th Oct - 50% of downstream timber piles driven into place

22nd Oct

4th November - upstream canoe portage piling complete and old boaters landing removed

16th Nov

7th Dec - no work being undertaken due to flooding

7th Dec

7th Dec

22nd Dec - Works Stopped for Christmas

22nd Dec

22nd Dec

22nd Dec

7th Jan 2010

7th Jan 2010

7th Jan 2010

13th Jan

13th Jan

13th Jan

17th Jan - site impossible to access due to flooding

25th Jan

25th Jan

25th Jan - new steps to be located here

5th Feb - new steps being installed

5th Feb - upstream walkway to the bank

5th Feb - upstream canoe portage platform

5th Feb - upstream boaters landing

15th Feb - lower landing 99% complete!

15th Feb - lower landing 99% complete - just the old steps to be removed

15th Feb - Upstream canoe landing just poking above the flood water.

 |