Allington Lock and Slipway
Gateway to the rural River Medway
Home
Information for all boaters and canoeists
How to find us
Contact Us
Photos and other useful information
FAQs
Eldridges Lock Canoe Fishway 2009/10
Replacement of Teston Lock Landing Stages 2009/10
Replacement of East Farleigh Lock Landing Stages 2009/10
East Lock Canoe and Fish Pass
Refurbishment of Allington Sluice
Allington Lock Security Barriers
Tonbridge Lock Gate Walkways
Rye Slipway Jetty
Reconstruction of Hampstead Lock 2009
Improvements for boaters 2009
Porters Lock Canoe Fishway 2008/09
River improvements 2006-2008
Improvements coming soon...
Photos - Allington
Photos - Medway general
Useful Links
Eldridges Lock Canoe Fishway 2009/10

The photos below show a record of progress of the installation of a new combined canoe and fish pass at Eldridges Lock on the River Medway, 1 mile West of Tonbridge in Kent. These works are being undertaken in Autumn/Winter 2009.
This combined pass, the second of its type in the UK (the first being at Porters Lock just 1.5 miles downstream) is an 80 metre long concrete channel, 1.5 metres wide and 600mm deep. The difference between upstream and downstream water levels is 1.6 metres. the pass starts with an entrance pool that allows canoeists to line themselves up for the first slope. The first slope which is furnished with artificial reeds known as "fish brushes" runs for 20 metres at a gradient of 1 in 25. Canoeists then enter a 3 metre wide resting pool which runs level for 26 metres. At the end of this pool canoeists have room to line themsevles up for the final slope - again furnished with fish brushes. This slope is also 1 in 25 and runs for 20 metres. At the end of this slope the channel narrows to 1.2 metres. The reason for this is to provide a slightly greater water velocity at the exit which should provide good attraction flow for fish to find and then climb the pass.
The brushes within the pass perform 3 functions. 1. The brushes are soft enough to allow canoes to pass over them safely witout any damage. 2 the brushes are rigid enough to withstand water pressures and therefore provide eddies and back-currents to enable fish to climb the pass. 3. There are enough brushes in the pass to ensure that during low river flows the channel only demands 0.3 cummes (300 litres per second). This is essential for a river like the Medway which has a predominately clay based catchment with resulting low summer base flows.
To each side of the pass, the ground has been sloped at 1 in 3.5 and a Geotextile called Enkamat has been laid to reduce the risk of scour in flood flows.
The idea comes from the University of Kassel in Germany. The University has been extremely helpful in providing advice and guidance for this pass and Porters Lock Pass. The brushes have also been supplied by them.
The works have been designed by Halcrow Group Ltd and construction undertaken by Dean and Dyball Civil Engineering. The cost of the whole project including purchase of land, design, contract documentation, supervision, supply of the fish brushes and of course construction is around £200k.

The pass should be completed by Christmas 2009, but will not be opened until March 2010 due to the risk of flood flows causing damage to the freshly-laid banks of the pass. The banks rely on the growth of grass to "stitch" it together and as such this will not start occurring until Spring 2010. Until then, the gates of the adjacent lock will remain pinned open so that most flood flows will be pass through this route. Keep an eye on this website for updates.

If you require any further technical details of the pass, please contact Chris Downs at Halcrow Group 01732 424184.
For any details on canoeing on the Medway, please visit the Medway Canoe Trail website: www.medwaycanoetrail.co.uk

The plan of the works


Before works commence


29th Sep - excavation starts


1st Oct - excavation


5th Oct - excavation for this part of the channel complete and blinding laid down


5th Oct - sheet piles for entrance being driven


13th Oct - reinforcement mesh for parts of the base slab being laid


15th Oct - some of the concrete bases poured


20th Oct - general shot looking downstream showing one section of wall freshly filled with concrete



20th Oct - general shot looking upstream showing another section of wall just poured



23rd Oct upstream entrance showing the back of the newly installed sheet piles



23rd Oct - part of new left-hand concrete wall complete



29th Oct



29th Oct



3rd November



9th November - Fish Brushes delivered and awaiting installation



12th Nov



30th Nov - flooding stops work


30th Nov - flooding stops work


30th Nov - flooding stops work


7th Dec - floods start to receed




7th Dec. This photo shows the start of the installation of the black recycled plastic panels to protect canoes from damage.



22nd Dec - Works stopped for Christmas



22nd Dec



22nd Dec



22nd Dec


24th Feb - Still waiting for the flood season to end before water is let down the pass. Should be end of March subject to river flows.


24th Feb


24th Feb


HomeInformation for all boaters and canoeistsHow to find usContact UsPhotos and other useful informationFAQs