The photos below show the replacement of East Farleigh Lock Landing Stages. The works included lots of improvements, such as new canoe portage platforms, shallower and wider steps, and new footpath.
New upstream boaters landing

New upstream canoe portage platform

New footpath linking lock to downstream landing stage

New downstream canoe portage platform

New downstream boaters landing

CONSTRUCTION PHOTOS
Downstream before works commence

Upstream before works commence

9th Oct - Old downstream boaters landing stage removed

20th Oct - 75% of downstream piling on the boaters landing stage completed

27th Oct - working on the downstream canoe portage piling

16th Nov

17th Nov

7th Dec

22nd Dec

7th Jan 2010

7th Jan 2010

7th Jan 2010

13th Jan

17th Jan - looking upstream - all works stopped due to flooding

17th Jan - looking downstream

25th Jan

15th Feb

18th Feb

1st March - Flooding affecting the completion of the works once again

1st Mar - looking at downstream canoe portage platform. The top of the steps can just be seen

 |