The photos below show a record of progress of the replacement of East Farleigh Lock Landing Stages:
Downstream before works commence

Upstream before works commence

9th Oct - Old downstream boaters landing stage removed

20th Oct - 75% of downstream piling on the boaters landing stage completed

22nd Oct Piling 100% complete on boaters downstream landing stage

27th Oct - working on the downstream canoe portage piling

4th Nov - timber substructure to the downstream canoe portage being fitted

16th Nov

17th Nov

7th Dec - works stopped due to flooding

7th Dec

22nd Dec - Works stopped for Christmas

22nd Dec

22nd Dec

22nd Dec

22nd Dec

7th Jan 2010

7th Jan 2010

7th Jan 2010

13th Jan

13th Jan

17th Jan - looking upstream - all works stopped due to flooding

17th Jan - looking downstream

19th Jan

25th Jan

25th Jan

25th Jan

25th Jan

15th Feb

15th Feb

18th Feb

1st March - Flooding affecting the completion of the works once again

1st Mar - looking at downstream canoe portage platform. The top of the steps can just be seen

 |