 |
Below are photographs showing the refurbishment of Allington Sluice. This £2.7 million project runs over 2.5 years starting in July 2009. The main works include, new gates, lifting gear and gantry, repairs to the concrete structure, new fish pass and disabled access ramps. Works due for completion by 31st March 2011.
General shot - Allington Sluice. Green netting has been in place for a few years to prevent spalling concrete from falling

20th Oct - Bottom half of new gate (No. 3) ready to be lifted into place

20th Oct - Bottom half of new gate being lifted into place (5.6 tonnes)

20th Oct - Gate being lined up with slots

20th Oct - Gate being lowered slowly into place

17th Nov - gate 2 - existing old motors gearboxes and winding drums

17th Nov - gate 1 - new motors, gearboxes and winding drums

22nd Jan - underside of new gantry beams

22nd Jan - works start on Allington Sluice fish pass

22nd Jan - route of new fish pass cleared

22nd Jan - disabled access ramp to be installed here

24th Feb - sheet piles to form the walls of the fish pass are installed

24th Feb - excavator about to start to dig out between the sheet piles

24th Feb - Island side footpaths laid ready to receive the new disabled access ramps

15th March - excavation for the fish pass

26th March

26th March

26th March

16th June - fish pass upstream

16th June - fish pass upstream

16th June - fish pass upstream

16th June - fish pass downstream

16th June - gate No. 2 and lifting gear being replaced on the sluice

 |